Feed Me Data · The Data Almanac

AI Data Centers

96 of the largest AI data centers: where they are, who owns them, which labs use them, how much power they draw and how far along they are.

Sites
96
Countries
12
Power today
14.5 GW
On the map
83 (48 approximate)

Sites

Sort with the Site, Power and Status headings (Status sorts by the date of Epoch’s latest update). An owner or user marked “likely” or “speculative” carries Epoch’s own confidence; names in links are companies we follow.

All 96 sites

LocationOwnerUsed bySources
Anthropic-Amazon New Carlisle Project Rainier55001 Larrison Blvd, New Carlisle, IN 46552 United States Mapped by street address1,037Operating: 18 buildings as of Oct 19, 2026 Epoch projects 32 buildings by Mar 17, 2028
Epoch’s note

Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.

4 sources
Colossus 2 5420 Tulane Rd, Memphis, TN 38109 United States Mapped by street address
  • SpaceXAI
946Operating: 2 buildings as of Jun 15, 2026 Epoch projects 3 buildings by Feb 25, 2027
Epoch’s note

The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.

6 sources
Microsoft Fairwater Atlanta Microsoft AI WAN1435 Hwy 54 W, Fayetteville, GA 30214 United States Mapped by street address636Operating: 4 buildings as of Jun 14, 2026
Epoch’s note

Building 3 and 4 are operational.

4 sources
OpenAI Stargate Abilene Stargate5502 Spinks Rd, Abilene, TX 79601 United States Mapped to Abilene (approximate)618Operating: 6 buildings as of Sep 10, 2026 Epoch projects 8 buildings by Nov 1, 2026
Epoch’s note

Buildings 5-6 delivered to the customer. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now been delivered to the customer" (transcript). 618 MW = 6 x 103 MW, matching the per-building IT power figure Crusoe reported earlier. Since Oracle is the chip owner rather than the facility operator, we assume "delivered" means the chips are installed and ready to use.

3 sources
DayOne Nusajaya Malaysia Mapped to Iskandar Puteri (approximate)——473Operating: 10 buildings as of Oct 2, 2026
Epoch’s note

Buildings 7-10 are operational. Judging by their state in April 2026, we expect 3 months to finish construction and another 3 months to ramp to full capacity.

4 sources
Meta Prometheus Prometheus1 Community Cir, New Albany, OH 43054 United States Mapped to New Albany (approximate)471Operating: 10 buildings as of Aug 31, 2026 Epoch projects 18 buildings by Nov 30, 2026
Epoch’s note

Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.

3 sources
DayOne Kempas HP79+MP, 81300 Johor Bahru, Johor, Malaysia Malaysia Mapped to Johor Bahru (approximate)——422Operating: 9 buildings as of Oct 1, 2026
Epoch’s note

Buildings 7-8 assumed operational. These buildings were roofed by March 2026 and by August 2026 their cooling and backup power equipment looked complete. With an additional two months of commissioning after August we approximate their operability to this date.

4 sources
Microsoft Fairwater Wisconsin Microsoft AI WAN4800 90th St, Mount Pleasant, WI 53403 United States Mapped by street address369Operating: 1 building as of May 15, 2026 Epoch projects 2 buildings by Feb 20, 2027
Epoch’s note

The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.

5 sources
Google Pryor (North) 4581 Webb St, Pryor, OK 74361 United States Mapped to Pryor (approximate)368Operating: 2 buildings as of Sep 6, 2026
Epoch’s note

Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.

3 sources
Colossus 1 3231 Riverport Rd, Memphis, TN 38109 United States Mapped to Memphis (approximate)
  • SpaceXAI
340Operating: 1 building as of Jun 15, 2026
Epoch’s note

No major changes to the data center since February. Solar panels have been placed next to the facility.

5 sources
Google New Albany 1101 Beech Rd SW, New Albany, OH 43054 United States Mapped to New Albany (approximate)333Operating: 4 buildings as of May 18, 2026
Epoch’s note

Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.

2 sources
Google Columbus 5076 S High St, Columbus, OH 43207 United States Mapped to Columbus (approximate)303Operating: 4 buildings as of Aug 5, 2026 Epoch projects 5 buildings by Jul 1, 2027
Epoch’s note

Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.

2 sources
Amazon Madison Mega Site Project RainierAmazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County United States Mapped to Canton (approximate)284Operating: 5 buildings as of Jun 4, 2026 Epoch projects 7 buildings by Mar 1, 2027
Epoch’s note

Buildings 6 and 7 roof completed. Building 8 roof nearly completed. Building 9 roof half way up. No new operational buildings.

4 sources
CoreWeave Denton TX 8171 Jim Christal Rd, Denton, TX 76207 United States Mapped to Denton (approximate)262Operating: 7 buildings as of Sep 1, 2026 Epoch projects 8 buildings by May 31, 2027
Epoch’s note

Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.

4 sources
Bridge Data Centres MY06 Bridge Data Centres, Sedenak Tech Park, Johor, Malaysia Malaysia Mapped to Kampung Sedenak (approximate)
  • ByteDance (likely)
  • ByteDance (likely)
243Operating: 7 buildings as of Sep 13, 2026
Epoch’s note

No visible construction work on Buildings 8-10, but no cars in their carparks either (whereas Building 7 has many cars). So we still don't think Buildings 8-10 are utilized.

4 sources
Google Bristow 13001 Rollins Ford Road, Bristow, VA 20136 United States Mapped by street address238Operating: 3 buildings as of May 20, 2026
Epoch’s note

Building 3 is operational, based off of colored motion artifacts from cooling towers.

1 source
QTS Richmond 1 6000 Technology Blvd, Sandston, VA 23150 United States Mapped to Sandston (approximate)——238Operating: 5 buildings as of Feb 13, 2026
Epoch’s note

No changes to the site since December 2025.

2 sources
Google Council Bluffs (East) 10410 Bunge Ave, Council Bluffs, IA 51503 United States Mapped by street address237Operating: 3 buildings as of Jul 7, 2026
Epoch’s note

Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between buildings. Ground clearing to the southwest seems to be setting up for two more buildings.

2 sources
Google Omaha 11110 State St, Omaha, NE 68142 United States Mapped by street address237Operating: 3 buildings as of Jun 30, 2026 Epoch projects 4 buildings by Jan 23, 2028
Epoch’s note

Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.

2 sources
Google Papillion 14651-15249 Gold Coast Rd 68138 Papillion Nebraska, USA United States Mapped to Papillion (approximate)237Operating: 3 buildings as of May 4, 2026
Epoch’s note

Building 4 shell mostly complete, Building 5 steel framing is underway.

2 sources
Amazon Ridgeland Project Rainier1626 County Line Road Ridgeland, Mississippi United States Mapped by street address228Operating: 4 buildings as of May 15, 2026 Epoch projects 5 buildings by Feb 9, 2027
Epoch’s note

Buildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete. Building 5 roof is complete but still lacks cooling equipment.

4 sources
VNET Bayin Ulanqab 10 GW Hyperscale 2.0Bayin, Ulanqab, China China Mapped to Ulanqab (approximate)
  • VNET
  • ByteDance (speculative)
221Operating: 4 buildings as of May 6, 2026 Epoch projects 9 buildings by Sep 1, 2027
Epoch’s note

Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining. Previous building completion timelines would imply this building will be operational by the end of 2026.

4 sources
AWS New Albany 13360 Miller Rd NW United States Not on the map—213Operating: 9 buildings as of May 18, 2026 Epoch projects 14 buildings by Jul 1, 2027
Epoch’s note

Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.

4 sources
Microsoft Goodyear 14250 W Broadway Rd, Goodyear, AZ 85338 United States Mapped to Goodyear (approximate)202Operating: 4 buildings as of Apr 27, 2026
Epoch’s note

Foundations appear to be underway for Building 5 and 6, just north of Building 4.

3 sources
Microsoft Project Osmium 5855 SW Kerry St, Cumming, IA 50061 United States Not on the map190Operating: 4 buildings as of Jun 16, 2026
Epoch’s note

No notable changes since October.

4 sources
Huawei Horinger Huawei, Horinger, China China Not on the map
  • Huawei
—184Operating: 4 buildings as of Aug 18, 2026 Epoch projects 5 buildings by Feb 14, 2028
Epoch’s note

On the east zone, building 6 is under construction, and potentially larger than any of the identically sized buildings constructed thus far. Building 3 has not begun construction.

2 sources
Google Mesa United States Not on the map—183Operating: 2 buildings as of Aug 15, 2026
Epoch’s note

Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.

2 sources
Meta-QTS Hillsboro 2 4755 NE Huffman St, Hillsboro, OR 97124 United States Mapped by street address180Operating: 4 buildings as of Apr 17, 2026
Epoch’s note

All four buildings are operational.

2 sources
QTS Richmond 2 6030–6070 Technology Blvd, Sandston, VA 23150 United States Mapped to Sandston (approximate)——180Operating: 5 buildings as of May 14, 2026
Epoch’s note

Building 5 is estimated to be operational, based on the previous entry.

2 sources
Meta Jeffersonville 500 8th St, Jeffersonville, IN 47130, USA United States Mapped by street address178Operating: 2 buildings as of Jun 4, 2026
Epoch’s note

Building 1 and 2 are operational.

3 sources
Meta Rosemount 1772-2396 145th St, Rosemount, MN 55068, USA United States Mapped by street address178Operating: 2 buildings as of Jun 19, 2026
Epoch’s note

Buildings 1 and 2 are estimated to be operational.

2 sources
Meta Temple 2310 Eberhardt Rd, Temple, TX 76504 United States Mapped to Temple (approximate)178Operating: 3 buildings as of Sep 30, 2026
Epoch’s note

Building 3 is operational. Based on the stated completion date in this regulatory filing

3 sources
Alibaba Zhangbei Alibaba Zhangbei Yun Calculation Data Center, Zhangbei County, Zhangjiakou, Hebei, China, 076471 China Mapped to Zhangjiakou (approximate)169Operating: 6 buildings as of Jan 3, 2026
Epoch’s note

Expect Building 4-6 have finished upgrading with new chillers.

4 sources
Google Storey County United States Not on the map161Operating: 2 buildings as of Apr 13, 2026 Epoch projects 3 buildings by Jun 30, 2027
Epoch’s note

Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.

3 sources
Huawei Wuhu Wuhu, China China Mapped to Wuhu (approximate)
  • Huawei
—157Operating: 4 buildings as of Aug 6, 2026 Epoch projects 5 buildings by Nov 1, 2026
Epoch’s note

On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in approximately one month, given that it is structurally complete and 75% of its cooling looks to be installed. On the east campus, building 9 is under construction.

3 sources
Google The Dalles 3500 River Rd, The Dalles, OR United States Mapped to The Dalles (approximate)—154Operating: 2 buildings as of Apr 29, 2026
Epoch’s note

Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building.

2 sources
Meta Montgomery Co Rd 42, Montgomery, AL 36105, USA United States Mapped by street address153Operating: 2 buildings as of Jun 18, 2026 Epoch projects 4 buildings by Feb 2, 2027
Epoch’s note

We estimate Buildings 1 and 2 are operational.

3 sources
Meta Cheyenne Cheyenne, WY 82007, USA United States Mapped to Cheyenne (approximate)152Operating: 2 buildings as of Jul 25, 2026 Epoch projects 4 buildings by Feb 15, 2027
Epoch’s note

Both buildings estimated to be operational.

3 sources
Meta Kuna 601 Kuna Mora Rd, Kuna ID 83634 United States Mapped by street address152Operating: 2 buildings as of Jun 1, 2026
Epoch’s note

Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings.

8 sources
Meta Huntsville 5400 Prosperity Dr NW, Toney, AL United States Mapped to Huntsville (approximate)146Operating: 2 buildings as of Jun 2, 2026
Epoch’s note

We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.

2 sources
QTS Richmond 3 3525–3543 Portugee Rd, Sandston, VA 23150 United States Mapped to Sandston (approximate)——144Operating: 3 buildings as of May 14, 2026 Epoch projects 5 buildings by Feb 13, 2027
Epoch’s note

Building 2 and 3 are operational, based on the previous entry.

2 sources
Google Lincoln 5475 Cloud Ct, Lincoln, NE 68514 United States Mapped to Lincoln (approximate)—141Operating: 1 building as of May 12, 2026 Epoch projects 2 buildings by Oct 1, 2027
Epoch’s note

Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.

3 sources
Google Lancaster 105 Whiley Rd, Lancaster, OH 43130 United States Mapped by street address—137Operating: 2 buildings as of Mar 12, 2026
Epoch’s note

At this point, Building 1 and 2 have since already been operational. Additionally, there is visible steam showing clear evidence of operational for both before this date.

1 source
Meta Eagle Mountain 1275 N Community Cir, Eagle Mountain, UT 84005 United States Mapped to Eagle Mountain (approximate)133Operating: 2 buildings as of May 2, 2026
Epoch’s note

Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.

2 sources
Coreweave Helios 984 County Road 112, Afton, TX 79220 United States Mapped by street address132Operating: 1 building as of Aug 30, 2026 Epoch projects 3 buildings by Jan 1, 2028
Epoch’s note

Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.

4 sources
Meta Los Lunas 4250 Messenger Lp, Los Lunas, NM 87031 United States Mapped to Los Lunas (approximate)118Operating: 2 buildings as of Oct 26, 2026 Epoch projects 3 buildings by Jan 1, 2028
Epoch’s note

Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.

3 sources
YTL Johor YTL Green Data Centers, Kulai, Johor, Malaysia Malaysia Mapped to Kulai (approximate)——113Operating: 2 buildings as of Jul 13, 2026 Epoch projects 5 buildings by Aug 1, 2028
Epoch’s note

Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.

3 sources
AWS Berwick Project Rainier1125 Electron Ave, Berwick, PA 18603 United States Mapped to Berwick (approximate)108Operating: 3 buildings as of Aug 1, 2026 Epoch projects 4 buildings by Aug 1, 2027
Epoch’s note

Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.

4 sources
Google Kansas City East United States Not on the map—105Operating: 1 building as of Aug 1, 2026
Epoch’s note

Building 1 operational. Estimated based on present construction progress and typical timelines.

2 sources
Google Midlothian 3250 Railport Parkway, Midlothian, TX 76065 United States Mapped to Midlothian (approximate)—103Operating: 1 building as of Jul 1, 2026
Epoch’s note

Estimated full completion of the expanded row of cooling towers and backup generators for Building 1.

2 sources
Google Waltham Cross Land at Maxwell's Farm West, Great Cambridge Road, Cheshunt, EN8 8XH United Kingdom Mapped to Cheshunt (approximate)88Operating: 1 building as of Apr 23, 2026
Epoch’s note

Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image; no capacity change since September 2025.

4 sources
Meta Gallatin 1 Meta Lp, Gallatin, TN 37066 United States Mapped to Gallatin (approximate)87Operating: 1 building as of Aug 24, 2026
Epoch’s note

Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.

2 sources
STACK Infrastructure NVA02 9590 Hornbaker Rd, Manassas, VA 20109 United States Mapped by street address——85Operating: 1 building as of Feb 14, 2026 Epoch projects 6 buildings by Jan 1, 2028
Epoch’s note

All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.

3 sources
CoreWeave Chester VA 1401 Meadowville Technology Parkway, Chester, VA United States Mapped by street address82Operating: 2 buildings as of May 20, 2026 Epoch projects 3 buildings by Jun 30, 2027
Epoch’s note

Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.

3 sources
Meta Sarpy 14436-14998 Fairview Rd, Springfield, NE 68059, USA United States Mapped by street address80Operating: 1 building as of Aug 2, 2026
Epoch’s note

Building 1 is operational (estimate).

1 source
Google Arcola 42575 Arcola Blvd, Sterling, VA 20166 United States Mapped to Sterling (approximate)—77Operating: 1 building as of Jun 16, 2026
Epoch’s note

Building 1 is operational, based off of colored motion artifacts from cooling towers and direct visual verification.

1 source
Google Red Oak 330 Austin Blvd, Red Oak, TX 75154 United States Mapped by street address—77Operating: 1 building as of Feb 6, 2026 Epoch projects 2 buildings by Dec 1, 2026
Epoch’s note

Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone. The Building 2 substation also appears complete.

2 sources
Microsoft SAT40 15000 Lambda Drive, San Antonio, TX 78245 United States Mapped to San Antonio (approximate)—75Operating: 2 buildings as of Feb 4, 2026
Epoch’s note

Site has already been completed, with no more visible construction on any building.

2 sources
Nebius Mantsala Finland Mapped to Mäntsälä (approximate)75Operating: 3 buildings as of Jun 29, 2026 Epoch projects 4 buildings by Dec 31, 2027
Epoch’s note

All three buildings in the first phase are operational.

2 sources
Oracle Batam Indonesia Mapped to Batam (approximate)72Operating: 3 buildings as of May 6, 2026
Epoch’s note

The three buildings look unchanged since March.

5 sources
Meta Aiken 7601 State Hwy 105, Trenton, SC 29847, USA United States Mapped to Aiken (approximate)69Operating: 1 building as of Aug 7, 2026 Epoch projects 2 buildings by Nov 5, 2026
Epoch’s note

Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2.

2 sources
CoreWeave Ellendale ND 9685 87th Ave SE, Ellendale, ND 58436 United States Mapped by street address68Operating: 1 building as of Jun 30, 2026 Epoch projects 2 buildings by Dec 31, 2026
Epoch’s note

According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.

3 sources
CoreWeave Marble NC 155 Palmer Ln, Marble, NC 28905 United States Mapped by street address65Operating: 1 building as of May 6, 2026
Epoch’s note

Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online.

4 sources
Stream Phoenix 2950 S. Litchfield Road United States Mapped by street address——64Operating: 1 building as of May 1, 2026 Epoch projects 6 buildings by Jan 1, 2030
Epoch’s note

Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.

2 sources
Core42 Lake Mariner 7725 Lake Rd, Barker, NY 14012 United States Mapped by street address
  • Core42
58Operating: 2 buildings as of Jul 23, 2026
Epoch’s note

Both buildings still operational according to satellite imagery.

4 sources
Microsoft-Nebius New Jersey 3963 S Lincoln Ave, Vineland, New Jersey United States Mapped by street address50Operating: 1 building as of Jul 12, 2026
Epoch’s note

Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.

6 sources
Microsoft SAT14 3545 Wiseman Boulevard, San Antonio, TX 78251 United States Mapped by street address—47Operating: 2 buildings as of Mar 31, 2026
Epoch’s note

Building 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases Phase 2, Phase 3, and Phase 4 on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.

4 sources
Anthropic Lake Mariner 7725 Lake Rd, Barker, NY 14012 United States Mapped by street address
  • AI XPV Platform
42Operating: 1 building as of Jul 23, 2026 Epoch projects 2 buildings by Oct 31, 2026
Epoch’s note

Building 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.

3 sources
CoreWeave Norway Stølevegen 39, 4715 Øvrebø, Norway Norway Not on the map42Operating: 1 building as of Aug 15, 2026
Epoch’s note

Building 1 still operational. No new major developments since the April image, though the large land clearing to the southwest is now much more clearly visible. Bulk is saying this expansion could include AI datacenters, but we don't have any confirmation this expansion is for CoreWeave yet.

3 sources
Southgate Melbourne Australia Mapped to Melbourne (approximate)—41Operating: 1 building as of Aug 9, 2026
Epoch’s note

Building 1 is operational (estimate). No additional chip deployment beyond the 18,400 GB300 GPUs has been publicly confirmed, so we continue to report the disclosed capacity allocated to Project Southgate, rather than speculate on further buildout.

3 sources
Start Campus Sines Data Campus Start Campus - Sustainable Data Center Services, Sines, Portugal Portugal Mapped to Sines (approximate)33Operating: 1 building as of Aug 16, 2026 Epoch projects 2 buildings by Sep 30, 2027
Epoch’s note

Satellite imagery shows two black outlines, suggesting two buildings going up on a second adjacent site. There is an outline of another building as well. Further to the east, there is land clearing.

3 sources
Vantage TX1 14720 Omicron Dr, San Antonio, TX 78245 United States Mapped by street address——32Operating: 1 building as of Feb 15, 2026 Epoch projects 2 buildings by Aug 31, 2027
Epoch’s note

Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT power of 32 MW. Source

3 sources
CoreWeave Dalton 1 & 2 2205 Industrial South Rd, Dalton, GA, 30721 United States Mapped by street address28Operating: 1 building as of Feb 20, 2026
Epoch’s note

Building 1 is operational, given it was announced completed 4 months ago and looks completed in satellite imagery. All cooling/mechanical rows are installed, with no obvious active building construction visible.

4 sources
xAI QTS Atlanta 1025 Jefferson Street NW, Atlanta, GA 30318 United States Mapped by street address
  • SpaceXAI
  • SpaceXAI
17Operating: 1 building as of Jul 10, 2026
Epoch’s note

No significant change to the building since the August 2025 image.

3 sources
Nscale Keflavik Valhallarbraut 868, 262 Reykjanesbær, Iceland Iceland Mapped to Reykjanesbær (approximate)—5Operating: 1 building as of Jul 27, 2026
Epoch’s note

Building 1 is operational (estimate). Full campus visibly externally complete from satellite imagery. Virtually no active construction visible.

4 sources
Anthropic Barber Lake United States Not on the map
  • Cipher Mining
0Under construction as of Jul 30, 2026 Epoch projects 1 building by Dec 30, 2026
Epoch’s note

Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.

7 sources
CoreWeave Lancaster Greenfield site 216 Greenfield Rd, Lancaster, PA United States Mapped by street address0Under construction as of Jul 13, 2026 Epoch projects 1 building by Jun 30, 2027
Epoch’s note

Cooling install continues on the roof, satellite imagery indicates that not all units have been completed. Continued presence of construction vehicles and unfinished land on the campus suggests that the building is not operational yet.

2 sources
CoreWeave Muskogee OK 1525 W 43rd St S, Muskogee, OK 74401, USA United States Mapped to Muskogee (approximate)0Under construction as of Jun 13, 2026 Epoch projects 1 building by Dec 31, 2026
Epoch’s note

Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.

3 sources
Crusoe Abilene Expansion 5502 Spinks Rd, Abilene, TX 79601 United States Mapped to Abilene (approximate)0Under construction as of Jan 15, 2026 Epoch projects 1 building by Sep 17, 2027
Epoch’s note

Land clearing continues.

4 sources
EcoDataCenter 2 Kvarnsvedsvägen 420, 784 66 Borlänge, Sweden Sweden Mapped to Borlänge (approximate)0Under construction as of Aug 17, 2026 Epoch projects 2 buildings by Jun 30, 2027
Epoch’s note

Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed. Buildings 3-4 look like their foundations have been laid out and are early in construction.

4 sources
Envision Galaxy Ulanqab China Mapped to Ulanqab (approximate)——0Under construction as of Sep 5, 2026 Epoch projects 1 building by Nov 1, 2026
Epoch’s note

Land clearing begins for Building 4.

2 sources
Goodnight 10001 Lima Rd, Claude, TX 79019 United States Mapped to Claude (approximate)0Under construction as of Apr 16, 2026 Epoch projects 1 building by Mar 15, 2027
Epoch’s note

Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.

5 sources
Google Cedar Rapids 5800 EDGEWOOD RD SW CEDAR RAPIDS, IA 52404 United States Mapped by street address0Under construction as of Apr 16, 2026 Epoch projects 1 building by Dec 31, 2026
Epoch’s note

Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.

2 sources
Google Fort Wayne 6015 Adams Center Road, Fort Wayne, IN 46806 United States Mapped by street address0Under construction as of Aug 19, 2026 Epoch projects 1 building by Dec 1, 2026
Epoch’s note

Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.

4 sources
Meta Bowling Green 12356 Middleton Pike, Bowling Green, OH 43402 United States Mapped by street address0Under construction as of Jul 30, 2026 Epoch projects 1 building by Feb 1, 2027
Epoch’s note

Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place.

4 sources
Meta Hyperion HyperionHolly Ridge, LA 71269 United States Not on the map0Under construction as of Apr 19, 2026
Epoch’s note

Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.

4 sources
Microsoft Narvik Norway Norway Mapped to Narvik (approximate)0Under construction as of Jul 5, 2026 Epoch projects 2 buildings by Dec 31, 2026
Epoch’s note

Building 1 cooling looks complete. Backup generator install continues adjacent to B1. Building 2 cooling install continues. Backup generator concrete pads are there, but no equipment install visible. Cooling install appears to continue on Building 3. Construction equipment present all around site. We believe no buildings are operational at this time.

3 sources
OpenAI Stargate Lordstown Stargate2300 Hallock Young Rd, Warren, OH 44481 United States Mapped by street address
  • Softbank
0Under construction as of Jul 30, 2026 Epoch projects 1 building by Mar 1, 2027
Epoch’s note

Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.

3 sources
OpenAI Stargate Michigan StargateUnited States Not on the map0Under construction as of Mar 12, 2026 Epoch projects 3 buildings by Dec 31, 2028
Epoch’s note

Groundwork is visible for Building 1, at the left end of the site.

5 sources
OpenAI Stargate Milam StargateUnited States Not on the map
  • Softbank
0Under construction as of Mar 23, 2026
Epoch’s note

Steel framing and roofing is underway for Building 1.

3 sources
OpenAI Stargate New Mexico StargateUnited States Not on the map0Under construction as of Jun 22, 2026 Epoch projects 4 buildings by Dec 31, 2028
Epoch’s note

Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion.

3 sources
OpenAI Stargate Shackelford Stargate175 Private Road 1604, Abilene, TX 79601, Shackelford County United States Mapped to Abilene (approximate)0Under construction as of Sep 4, 2026 Epoch projects 1 building by Aug 15, 2027
Epoch’s note

Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.

4 sources
OpenAI Stargate UAE StargateNexus L&T Project Office, Al Bihouth, Al Dhafrah, Abu Dhabi, United Arab Emirates United Arab Emirates Mapped to Abu Dhabi (approximate)0Under construction as of Nov 16, 2025 Epoch projects 2 buildings by Dec 1, 2026
Epoch’s note

Building 1 and 2 are partly constructed. No clear evidence of more buildings starting construction.

3 sources
OpenAI Stargate Wisconsin StargateUnited States Not on the map0Under construction as of Jul 24, 2026 Epoch projects 4 buildings by Dec 31, 2028
Epoch’s note

Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.

2 sources
QTS Cedar Rapids 6200 76th Ave SW, Fairfax, IA 52228 United States Mapped by street address——0Under construction as of May 7, 2026 Epoch projects 3 buildings by Nov 15, 2026
Epoch’s note

Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.

4 sources
QTS Eagle Mountain 652 E Hyperscale Way, Eagle Mountain, UT 84013 United States Mapped to Eagle Mountain (approximate)0Under construction as of May 2, 2026 Epoch projects 2 buildings by Dec 31, 2026
Epoch’s note

Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.

2 sources

Data source: Epoch AI. Map placements: U.S. Census Bureau, GeoNames.

In the news

Recent data-center stories that name a company or project tracked here.

More in the Data centers topic

Where this comes from

Sites, owners, users, power and status: Epoch AI, “AI data centers(opens in a new tab)”. Published online at epoch.ai, under the Creative Commons Attribution license. Some status dates are Epoch’s own projections.

Map points: street addresses placed by the U.S. Census Bureau Geocoder(opens in a new tab); other sites placed at the town their address or name gives, from GeoNames(opens in a new tab) (CC BY 4.0(opens in a new tab)), and marked approximate. A site naming no town is not mapped. This page is not endorsed or certified by the Census Bureau.

Last refreshed Oct 29, 2026.

Keyboard shortcuts

On. Switch them off if they collide with your assistive tools; ? still opens this sheet.

Go to

Press g then the letter.

  • gh Latest
  • gs Sources
  • gm Media
  • gv Videos
  • gp Podcasts
  • gc Calendar
  • gd Decoder
  • gz Dataviz
  • ga Datasets
  • gb Blog
  • gk Markets
  • gj Careers
  • gn Prompt Notebook

On this page

  • / Focus search, where there is one
  • t Back to top
  • ? This list
  • Esc Close